bandeira do idioma
bandeira do idioma
Log in to SETE
click tariff logo, a snapshot of tariff projections by TR Soluções
Return

electricity tariffs, tr soluções, compulsory loan, light, tariff adjustment

May 14, 2025

Estimated Tariff Impacts of Items From the Bill Addressing the Proposed Power Sector Reform


Based on the internal draft of the Bill (PL) on the proposed power sector reform, announced by Minister Alexandre Silveira on 4/16/2025, TR Soluções used simulations run in SETE to quantify the tariff impact of the following topics highlighted in the draft:

  1. Opening the ACL to low voltage;
  2. Change to the CDE allocation trajectory by voltage level;
  3. Expanding the pool of consumers eligible for the Social Electricity Tariff;
  4. The CDE_GD charge as a TUSD tariff element instead of a TE element;
  5. Allocating Angra 1 and 2 nuclear energy in a format similar to Proinfa quotas.

Using version 14.88 of SETE as a reference, the combined average annual impacts of these five measures result in variations to the base tariff projections for 2026, Brazil average, at High Voltage (above 44 kV), Medium Voltage (between 2.3 kV and 44 kV), and Low Voltage (below 2.3 kV, subgroup B1), as described in Table 1.

Table 1 - Annual Impact of the Combined Effects

Annual impact of the combined effects

Source: TR Soluções, SETE platform.

In Table 1, we can see that the combined effects' impact on Application Tariffs (TUSD + TE) for consumer units in the different groups is relatively similar. However, there's a clear reallocation of costs among tariff components, resulting in a reduction in Electricity Tariffs (TE) and an increase in Distribution System Usage Tariffs (TUSD). This effect tends to intensify as the load's connection voltage level to the distribution system rises. That means that, in the end, the "bill" for this proposed power sector reform will be paid, via the TUSD, mostly by industrial consumer units at High Voltage (HV).

To let SETE users run similar simulations, TR Soluções describes throughout this document how the possible effects of these five measures were simulated.

It's important to stress that, to quantify the combined effects, the simulations involving changes to the energy balance, items 1 and 5, must be run before the simulations for the other movements (items 2, 3, and 4).

1. Opening the ACL to Low Voltage

Since SETE version 14.48, released on November 24, 2022, a tool has been available to simulate the possible opening of the ACL to the Group B market.

This tool can be found at: Menu/Tools/Energy/Market Liberalization, under the "LV Market" tab. In market-liberalization simulations, users must fill in the following fields:

  1. ACL Opening Start Date for Group B;
  2. Monthly Migration Speed as % of Group B energy;
  3. Allocation % of Migration to Incentivized Source;
  4. Discount % of Migration to Incentivized Source.

In the simulation run for this item, TR Soluções used the following data for the respective fields: 3/1/2027; 0.5%; 0%; 0%. The average annual impacts of this measure result in variations to the base projections, for 2026, of High, Medium, and Low Voltage tariffs, Brazil average, as described in Table 2.

Table 2 -Annual Impact of Opening the ACL to LV

Annual impact of opening the ACL to LV

Source: TR Soluções, SETE platform.

2. Change to the CDE Allocation Trajectory by Voltage Level

SETE version 14.88, released on May 12, 2025, lets users change the CDE's reference tariff so any allocation can be implemented between submarkets and between voltage levels. It's available at: Menu/Flags and CDE/CDE, "CDE" tab, at the bottom of the page, in the table titled "Allocation and Tariff," "Allocation" tab. There, you'll find a table with the current tariff structure, which provides, through 2030, for a transition toward equalizing the CDE between the S/SE-CO and N/NE submarkets, as well as differentiation between voltage levels.

To simulate the effects of the guidelines proposed in the reform text, users just need to keep the standard allocation between submarkets (since the bill draft doesn't signal any reversal of the ongoing equalization), keep the 2025 allocation between 2026 and 2029, and, starting in 2030, begin the new transition, per Table 3.

Table 3 -CDE Allocation Between Submarkets and Voltage Levels per the Reform Bill Draft

CDE allocation between submarkets and voltage levels per the reform bill draft

Source: TR Soluções, SETE platform.

The average annual impacts of this measure result in variations to the base projections, for 2026, of High, Medium, and Low Voltage tariffs, Brazil average, as described in Table 4.

Table 4 - Annual Impact of the CDE Allocation Proposal

Annual impact of the CDE allocation proposal

Source: TR Soluções, SETE platform.

At the end of the transition cycles for allocating the CDE quota by voltage level, expected for 2038, consumer units connected at High Voltage (HV) should pay the same CDE quota amounts charged to units connected at Low Voltage (LV). Compared to current quotas, that represents an increase of approximately 57% in the quota value for HV loads, while LV loads will see a 23% reduction.

3. Expanding the Pool of Consumers Eligible for the Social Electricity Tariff

In the calculation results the MME published in its presentation on April 16, the additional funds needed for the "New Social Tariff" would be BRL 3.6 billion per year. To simulate this item's impact on the tariff, SETE users just need to build a CDE_Usage-quota projection scenario, adding that increase to the total amount.

Table 5 - Annual Impact of the New Social Tariff

Annual impact of the New Social Tariff

Source: TR Soluções, SETE platform.

To change the annual CDE_Usage quota, go to: Menu/Flags and CDE/CDE, "CDE" tab, table titled "My CDE Quota Projections," and add BRL 3.6 billion to the table's value, or any other amount you'd like to simulate the impact of.

The average annual impacts of this measure result in variations to the base projections, for 2026, of High, Medium, and Low Voltage tariffs, Brazil average, as described in Table 5.

4. CDE_GD Charge as a TUSD Tariff Element Instead of TE

The change to CDE_GD allocation, currently borne only by captive consumers and therefore included in the Electricity Tariff (TE), proposes treating CDE_GD as a CDE_Usage expense. To simulate this change in the charge's allocation, just add the projected CDE_GD amounts, available at: Menu/Flags and CDE/CDE GD, to the CDE_Usage quotas. It's important to also zero out, under My Projections, the annual figures previously shown for CDE_GD quotas.

To change the annual CDE_Usage quota, go to: Menu/Flags and CDE/CDE, "CDE" tab, table titled "My CDE Quota Projections," and add the CDE_GD-related amount to the table's value.

The average annual impacts of this measure result in variations to the base projections, for 2026, of High, Medium, and Low Voltage tariffs, Brazil average, as described in Table 6.

Table 6 - Annual Impact of Moving CDE_GD to the TUSD Instead of the TE

 Annual impact of moving CDE_GD to the TUSD instead of the TE

Source: TR Soluções, SETE platform.

By allocating CDE_GD to the TUSD, the current CDE_GD cost's allocation base expands, since it now also includes the universe of ACL consumer units.

5. Allocating Angra 1 and 2 Nuclear Energy in a Format Similar to Proinfa Quotas

Under the reform bill's proposal, energy from the Angra 1 and 2 nuclear plants would stop being part of distribution companies' energy-purchase contract portfolio, and instead be treated as a charge, in a format similar to the Incentive Program for Alternative Sources of Electric Energy (Proinfa). This move implies expanding the nuclear plants' allocation base to include free consumers.

To simulate this change in SETE, just remove the Angra 1 and 2 contracts and add the same amount and corresponding price to one of Proinfa's sources (PCH, Wind, or Biomass).

In the simulation run for this item, TR Soluções chose "Biomass" as the Proinfa source aggregating the costs and energy related to the Angra 1 and 2 plants. To do so, it was necessary to indicate the annual energy volumes, as well as the corresponding tariffs tied to the nuclear plants' costs.

For the energy data, TR Soluções simply added the energy related to the two nuclear plants to the current Biomass contracting scenario. As for annual tariffs, TR Soluções calculated average tariffs, weighted by each source's market (biomass and nuclear).

Table 7 - "My Proinfa Projections" Table Simulating Angra 1 and 2's New Allocation

'My Proinfa Projections' table simulating Angra 1 and 2's new allocation

Source: TR Soluções, SETE platform.

In the simulation run for this item, the "My Projections" table, "Biomass" source, was filled in by TR Soluções with the prices and amounts shown in Table 7.

Table 8 -Annual Impact of Changing the Treatment of Angra 1 and 2's Energy

Annual impact of changing the treatment of Angra 1 and 2's energy

Source: TR Soluções, SETE platform.

The average annual impacts of this measure result in variations to the base projections, for 2026, of High, Medium, and Low Voltage tariffs, Brazil average, as described in Table 8.

TR Soluções remains available to SETE users to clarify any questions about the calculations presented in this document, and to help reproduce the calculations so it's possible to see the effects on specific distribution companies' tariffs.

* TR Soluções Regulatory Team.